Projects

Ridgecrest Reservoir
Construction of the 2 million gallon
Ridgecrest Reservoir was completed on December 13, 2005. The project added needed storage to the 1050 pressure zone in Diamond Bar.
Sacrificial Anode Program
The District initiated this program in 2002
to reduce the number of service lateral failures throughout the District
and provide reliable water service to customers for years to come.
The anticipated cost to install sacrificial anodes on all metered
services is $820,000. The installation of these anodes will stabilize
the system and potentially eliminate corrosion of service lateral
components that have been known to fail from pin-hole leaks. Such leaks can result in service interruptions to District customers. To date, District
staff has installed over 5,000 zinc anodes to provide cathodic protection
and extend the life of existing service lateral components.
|